Manufacturing and Technical Data Package Review

FIRST ARTICLE INSPECTION (AS9102 GUIDELINE)

It must be recognized that there has been serious escapes with both internally-built hardware and hardware delivered by External Providers; and a stringent First Article Inspection (FAI)/ Product Review (PR) process is one change that is focused on improving your Organization's performance! 

AQT attacks FAIs with the following simple methodologies: 

Incorporates Three Elements:

  1. External Provider Capability Assessment

  2. Table-Top Review

  3. Test, Qualification & Verification

Note:

•Requires visual inspection at appropriate magnification depending upon given commodities

•All new product/designs require a FAI/PR

•Document objective evidence that all three elements have been completed

•Two FAI/PR Levels:

–Level I – Mission Critical designs, Complex/Critical product

–Level II – All products not deemed Level I, e.g., simple mechanical, electrical, optical


The TWO LEVELS OF FAI/PR are defined as follows:

Level I – The complete FAI/PR is imposed on mission critical designs, new designs of complex/critical product, and/or an established mission-critical complex/critical product that meets one or more of the following criteria:

  • New Part Number

  • Change in manufacturing location

  • Gaps in manufacturing of greater than 12 months

  • Product or Supplier failure history

  • Mission Critical change in the Bill of Material

  • Sub-tier changes

  • Major changes in the design

Level II – This modified FAI/PR is implemented on first pieces of all products not deemed to require a Level 1 First Article Inspection/Product  Review. 

–Example:  simple mechanical, electrical and optical parts.

Please contact AQT to discuss details of the process and how our FAI Expertise can be applied to the requirements of your Organization. 

First Article Inspection (AS9102 Guideline): Our Services